Highlights
- Equipment testing is underway at Malawi's Kangankunde project, with first rare earth concentrate targeted for December 2026.
- Lindian holds A$45.1 million in cash and A$17 million in undrawn bank facilities, though conditions for accessing those funds remain unclear.
- Carester's offtake covers 70% of heavy rare earth carbonate actually produced—not a guaranteed purchase of all output.
- The Deep Blue Sea litigation was remanded to Malawi's High Court and remains unresolved, adding legal uncertainty for investors.
- Integrated commissioning is scheduled for late November, with ore introduction and export logistics still representing critical execution gates.