Highlights
- Ucore hired Process Engineering Associates as owner's engineering representative for its Louisiana rare earth separation project.
- The first 600-tonne-per-year processing line targets installation, testing and commissioning in the first half of 2027.
- Ucore's broader Louisiana plan targets approximately 9,600 tonnes per year of capacity, subject to funding, permits and scale-up.
- Bryan Peak named project manager and Brad Laeger construction manager, joining an expanding on-site leadership team.
- Commissioning milestones are progressing, but commercial production and customer qualification remain the critical tests ahead.