Iluka Resources (ASX: ILU) is an Australian mineral sands company based in Perth and a major producer of zircon and titanium feedstocks. Its rare earths business is the Eneabba refinery in Western Australia, which is designed to turn monazite and xenotime concentrate into separated rare earth oxides for permanent magnets. REEx follows Eneabba closely because it is built to separate dysprosium and terbium. As of October 2026, China’s hold on heavy rare earth separation is even tighter than its hold on the light elements, as REEx has reported.

When will Iluka’s Eneabba refinery be complete?

As of October 21, 2026, Iluka has scheduled commissioning of the Eneabba rare earths refinery for mid-2027, according to its June 22, 2026, update to the ASX. Construction was 60% complete at Iluka’s August 2026 half-year results. In June, Iluka said it expected to reach 75% by the end of 2026.

Iluka’s indicative timeline puts construction completion, the start of commissioning and first oxides in 2027. Ramp-up follows through 2028. So mid-2027 is when the plant starts running. Full output is a 2029 target. Iluka’s first customer contract starts deliveries in 2028, during the ramp-up.

How the Eneabba timeline has moved

The target date has slipped since Iluka made its investment decision, and the cost estimate rose with it. Iluka pointed to inflation across major Western Australian resources projects. Front-end engineering then firmed up the new, higher estimate. The Australian Government increased its loan by A$400 million, and Iluka added A$214 million of its own cash.

Item What Iluka reported Source
Schedule and cost
Investment decision First production expected 2025; capital cost A$1.0 to 1.2 billion ASX, April 4, 2022
Cost revision Commissioning scheduled for 2026; capital estimate narrowed to A$1.7 to 1.8 billion Full-year results, February 21, 2024
Funding reset Commissioning expected in 2027; government loan increased by A$400 million; Iluka cash equity increased by A$214 million ASX, December 6, 2024
Indicative timeline 2027: construction complete, commissioning begins, first oxides. 2028: ramp-up. 2029: ramp-up complete. Iluka labels this timeline indicative only Investor presentation, May 6, 2026
June 2026 update Over 50% complete; commissioning scheduled for mid-2027; 75% complete expected at the end of 2026 ASX, June 22, 2026
Latest reported 60% complete; A$1.1 billion spent to July 31, 2026; commissioning 2027; capital estimate reaffirmed at A$1.7 to 1.8 billion Half-year results, August 19, 2026
Capacity
Concentrate feed 55,000 metric tons per year Half-year results, August 19, 2026
Total rare earth oxide 23,000 metric tons per year Half-year results, August 19, 2026
NdPr oxide 5,500 metric tons per year with additional feed, subject to feed mix; about 3,500 from the Eneabba stockpile alone, once ramped up ASX, June 22, 2026
Dy/Tb oxide 750 metric tons per year with additional feed, subject to feed mix; about 170 from the Eneabba stockpile alone, once ramped up ASX, June 22, 2026
Funding
Government loan A$1.65 billion, non-recourse to Iluka’s mineral sands business, through the Critical Minerals Facility run by Export Finance Australia. Tranche 1 is A$1.25 billion; the remaining A$400 million was confirmed available in June 2026 ASX, June 22, 2026
Iluka cash equity A$414 million, including A$82 million for commissioning working capital Investor presentation, May 6, 2026
Cost overrun facility A$150 million, shared equally; Iluka guarantees the government’s share ASX, December 6, 2024
Loan repayments Begin at project completion or December 2027, whichever comes first; scheduled repayments based on available feed; term extendable to 2038 unless feed sources are forecast to run out earlier Investor presentation, May 6, 2026
Royalty to Iluka Up to A$81 million a year, capped at A$900 million in total. Capped at A$40 million a year for the first four years of production if Iluka does not extend feed at least two years beyond the stockpile’s projected use ASX, December 6, 2024
Customers and feed
First offtake Unnamed global automotive company; 1,200 metric tons of Nd, Pr, Dy and Tb oxides over four years from 2028; take-or-pay on 90% of volumes; minimum revenue at minimum prices US$155 million; about 10% of planned production over the term ASX, June 22, 2026
Eneabba stockpile 1.2 million metric tons of ore (half-year results, August 19, 2026); enough to feed the refinery to about 2035 (investor presentation, May 6, 2026) Half-year results; investor presentation
Construction
Contractors Fluor (engineering, procurement and construction management); Civmec (structural, mechanical, piping, electrical and instrumentation works) Fluor, June 21, 2022; ASX, June 22, 2026
Equipment Engineering complete; almost all major equipment on site, including the roaster kiln Quarterly review to June 30, 2026
Verified October 21, 2026 against Iluka’s ASX releases and investor presentations. Dollar figures are Australian dollars except the offtake revenue, which Iluka reports in US dollars. Dates from 2024 onward are for commissioning, which comes before first production. Iluka’s quarterly review to September 30, 2026, had not been released at the time of verification.

What will the Eneabba refinery produce?

Alongside separated oxides, Eneabba will make a range of carbonate products. Its light rare earth circuit makes neodymium and praseodymium oxide (NdPr). Its heavy rare earth circuit makes dysprosium and terbium oxide. Concentrate is cracked in a roaster kiln, then leached, purified and separated by solvent extraction before the oxides are finished and bagged. In its August 2026 results, Iluka gave the plant a capacity of up to 5,500 metric tons a year of NdPr oxide and 750 of Dy/Tb oxide.

Feed decides how close Eneabba gets to those numbers. On the Eneabba stockpile alone, a footnote in Iluka’s June 2026 offtake notice puts output at about 3,500 metric tons a year of NdPr oxide and 170 of Dy/Tb oxide. That is nearly two-thirds of NdPr capacity and under a quarter of Dy/Tb capacity. Heavy rare earth output therefore depends on feed from beyond the stockpile, much of it from other companies.

How is the Eneabba refinery funded?

As of June 2026, the Australian Government is funding most of Eneabba through an A$1.65 billion loan from the Critical Minerals Facility, administered by Export Finance Australia. The loan is non-recourse to Iluka’s mineral sands business. It is repaid from refinery cash flow and, according to Iluka’s investment decision presentation, secured over the Eneabba plant and stockpile.

Iluka adds its own cash equity. It also shares a cost overrun facility with the government and guarantees the government’s half. The final A$400 million tranche depended in part on Iluka signing offtake terms the government found satisfactory. In June 2026, Iluka said Export Finance Australia had confirmed access to the full loan.

The deal also pays Iluka a royalty from refinery cash flow. That royalty is capped lower for the first years of production unless Iluka extends feed at least two years beyond the stockpile’s projected use. In REEx’s reading, the structure rewards Iluka for filling the plant.

Where will Eneabba get its feedstock?

Eneabba’s first feed is Iluka’s own stockpile at the site, which Iluka has built up since the early 1990s from its mineral sands operations. To run the plant closer to capacity, Iluka’s August 2026 presentation lists these other feed sources:

  • Lindian Resources, monazite concentrate from Kangankunde in Malawi
  • Northern Minerals, xenotime concentrate from Browns Range in Western Australia
  • VHM, concentrate from Goschen in Victoria
  • Iluka’s own Balranald operation in New South Wales and its proposed Wimmera project in Victoria

As of Iluka’s August 2026 presentation, several of those sources were not yet producing mines. The presentation stated that VHM’s Goschen, Iluka’s Wimmera and Northern Minerals’ Wolverine deposit had not reached a final investment decision, and that there was no certainty they would proceed.

Of the feeds in Iluka’s August 2026 presentation, Northern Minerals’ Wolverine xenotime is the richest in dysprosium and terbium. Iluka’s presentation, citing Northern Minerals, described Browns Range as progressing toward an investment decision, with first production anticipated in late 2028 or early 2029. That was before Northern missed its September 30, 2026, investment target. REEx reported the missed deadline and tied it to incomplete project financing and a dispute with China-linked shareholders. REEx has also covered Iluka’s long-term feedstock deal with Lindian and Kangankunde’s progress toward first concentrate.

What are the risks to the Eneabba schedule?

By mid-2026, engineering was finished and almost all major equipment, including the roaster kiln, was on site. The risks REEx watches from here are in commissioning, ramp-up and feed.

Loan repayments begin at project completion or December 2027, whichever comes first. Either way, that is before the 2028 ramp-up year. Scheduled repayments are tied to available feed, and the term can extend to 2038. In REEx’s reading, that lets the loan absorb a slow ramp-up, with most of the cost landing on the cash Iluka takes out of the refinery.

As of October 2026, REEx’s view is that the build is on track for mid-2027 commissioning. Magnet buyers should also watch when Northern Minerals resets its Browns Range investment decision. For the wider picture, see REEx’s analysis of the coming Western separation bottleneck and its earlier look at the questions Iluka investors are not asking.

Frequently asked questions

Is Eneabba Australia’s first rare earth refinery?

Yes, in the sense Iluka uses. As of October 2026, Eneabba is set to be Australia’s first fully integrated refinery for separated light and heavy rare earth oxides. Concentrate goes in and finished oxides come out at one site. Lynas Rare Earths already produces separated rare earths, but its separation plant is in Malaysia, with cracking and leaching at Kalgoorlie in Western Australia.

Where is the Eneabba refinery?

The refinery is at Iluka’s Eneabba site in Western Australia’s Mid West region, roughly 300 kilometers north of Perth. It sits beside the stockpile that supplies its first feed. Iluka developed the site in phases: earlier phases screened and concentrated stockpile material, and the refinery turns that concentrate into separated oxides.

Who is building the Eneabba refinery?

Fluor is the engineering, procurement and construction management contractor, appointed in June 2022 after Iluka’s investment decision. Iluka announced Civmec’s contract for structural, mechanical, piping, electrical and instrumentation works in June 2026. The refinery belongs to a special purpose entity owned by Iluka. That entity is the borrower under the government loan.

Who is buying rare earths from Eneabba?

Iluka’s first offtake customer, announced in June 2026, is a global automotive company it did not name. The contract, take-or-pay on 90% of volumes, covers neodymium, praseodymium, dysprosium and terbium oxides for four years starting in 2028. That is about 10% of Iluka’s planned production over the term. When it announced the deal, Iluka said talks with other customers were continuing. REEx covered the deal in Iluka’s first major rare earth customer.

How much will the Eneabba refinery cost?

As of October 2026, the latest figure is from Iluka’s August 2026 half-year results, which reaffirmed a capital estimate of A$1.7 to 1.8 billion. That is well above the A$1.0 to 1.2 billion estimate at the investment decision. Iluka linked the rise to inflation across major Western Australian resources projects. Iluka says the project is fully funded through the government loan and its own equity.

This profile is independent analysis and is not investment advice. Figures change, so check Iluka’s latest ASX releases before relying on them.

Investor Snapshot

Membership Required

You must be a member to access this content.

View Membership Levels

Already a member? Log in here

Operations & Materials

Membership Required

You must be a member to access this content.

View Membership Levels

Already a member? Log in here

Corporate Structure

Membership Required

You must be a member to access this content.

View Membership Levels

Already a member? Log in here
REEx Intelligence

Recent Articles

Straight Into Your Inbox

Straight Into Your Inbox

Receive a Daily News Update Intended to Help You Keep Pace With the Rapidly Evolving REE Market.

Fantastic! Thanks for subscribing, you won't regret it.